Posts in: Shed Build Log

96F. Partly cloudy.

Side wall siding complete. Rear soffits complete.

95F. Partly cloudy.

Side wall siding partially complete.

100F. Partly cloudy.

Brick molding installed around doors. Siding on rear wall + beginning on side walls.

97F. Clear.

Front aesthetic walls framed.

92F. Clear.

Remaining french door installed.

87F. Mostly cloudy.

Remaining window installed (unpictured). One of two french doors installed.

94F. Clear.

Building paper has been removed from door entrances. A window has been installed.

Tyvek cut back. One of two windows installed & flashed.

94F. Clear.

Structure covered in building paper

House wrap is on.

86F. Mostly cloudy.

Roof system completely installed

Roof is complete. All drip edge installed. Still left to do, caulking and painting of fascia.

82F. Mostly cloudy.

A view of the roof, shingles complete

Finished shingling the roof. Special thanks to @milsyobtaf @catsilo and Rachel for putting in work.

Fun fact, what Rachel and I were able to complete in 6 hours the day previous, the four of us did in just over an hour and a half.