Posts in: Shed Build Log

Material delivery. No progress- materials weatherized for incoming winter storm.

Note: The only thing that is correct in this material order is the plywood panels. Everything else is wrong. Lowe’s Pro Desk has been underwhelming. I’ve spent more time emailing and calling to get the correct materials, than I have been building.

Pile of lumber.

Progress paused, awaiting material delivery.

Shopping day. Doors, windows, and flooring acquired from ReStore. Big discounts baybee.

Prehung doors waiting to be installedA pile of flooring still in boxes.

55F. Sunny. Subfloor decking complete. Special thanks to @milsyobtaf for assisting on the install.

Decked subfloor

52F. Sunny. Rigid insulation installed in between floor joists & caulked.

Insulated floor framing

50F. Drizzly. Floor frame squared & secured to skids. Battens installed for floor insulation.

Framed floor with battens between joists.

50F. Rainy. No work done.

60F. Floor framing complete; hammered 256 nails today, not counting misfires. All fingers healthy.

Framed floor with 2 by 6 lumber.

50F. Spent the day waiting on a material order to be ready.

A pile of lumber

45F. Sunny. Foundation footings complete; skids level to earth.

Skids sitting atop foundation footings

Bones, a 13-year old golden retriever looking handsome and noble. Trapezoidal foundation footings made of aggregate and decomposed granite.